Project delivery worksheet
Project delivery check: schedule buffer and cost forecast
Check a simplified delay against your schedule buffer and compare forecast cost with budget. Local calculations, visible assumptions and a copyable review brief.
Local worksheet · fictional sample available
Test your delivery assumptions
Your comparison
Figures are conditional on your inputs. Validate the estimate and authority before acting.
Enter values or load the fictional example to begin.
What this check does
Compare a delay on an assumed driving path with your remaining buffer. Separately compare actual cost plus an estimate to complete against the approved budget. All durations must use the same working-day calendar; all costs must use the same currency and accounting basis.
This simplified worksheet does not find the critical path, calculate earned value, model probabilities or approve a baseline change. Enter aggregate or fictional figures only. Values stay in this page, are not stored, and are not sent. No analytics runs here.
A transparent worked example
A three-day delay with two days of remaining buffer leaves a one-day gap beyond the commitment, assuming the delayed work drives completion and no recovery occurs. Actual cost of 12,000 plus remaining cost of 10,000 gives a 22,000 forecast. Against a 20,000 budget, the variance is +2,000 (+10%); positive means over budget.
If the delay is not on the driving path, analyse the network before using this result. Check for duplicated or missing commitments in the cost estimate. A number is a starting point for a review, not evidence that the estimate is complete.
Use the result to prepare a decision
Ask what evidence could change the forecast, which option remains available, who can approve it and when the decision is needed. Preserve the baseline until an authorised change is recorded. Use the status-report template to explain the result and its uncertainty.